keyboard_arrow_left See all news

Recent News

26 Sep, 2022 /
Seawork Press FP
World’s most advanced 100% electric passenger ferry unveiled
Leading maritime design and applied technologies company Artemis Technologies has unveil...
23 Sep, 2022 /
Seawork Press FP
New firefighting pair join the brigade
Two new fire boats have entered service on the River Thames, London, UK for the London F...
22 Sep, 2022 /
Seawork Press FP
Come on in - the marine world is lovely
The push to recruit the skilled workforce of tomorrow is underway across the marine indu...
22 Sep, 2022 /
Seawork Press FP
New class to be developed to support FOWT
A new class of vessel that will be capable of supporting the next big development in off...
20 Sep, 2022 /
Seawork Press FP
Designing for decarbonisation
Vessel hull design is an intrinsic component of decarbonisation. Balancing the hull form...
24 Oct, 2019
keyboard_arrow_left See all news

Logistics on land and sea - case study

Long-term Seawork exhibitor Williams Shipping is well-known for its capabilities on land and sea. A large project for ALE last month drew on this specialist expertise.

The former Murco refinery at Milford Haven has been undergoing works to convert it into a petroleum storage and distribution depot since 2015. Parts of the dismantled facility needed to be removed, with some destined for reuse overseas.

The first stage of the job was for ‘Willpower’ to tow the ‘Terra Marique’ from Hampshire to Pembroke.

‘Terra Marique’ is a vessel with unique beach landing and cargo loading features, making it possible to load the vessel from a wide range of quays and coasts. While ‘Terra Marique’ does have its own engines, when it comes to travelling longer distances it is usually faster and more economic to be towed by a workboat such as ‘Willpower’. With a free running speed of 12knots and bollard pull of 28.4t, ‘Willpower’ is often used for these types of project – earlier in the year she was used to bring the new ‘Red Kestrel’ ferry to Southampton from Liverpool.

Meanwhile, 6 Williams Shipping trucks with flatbed trailers had relocated to Pembrokeshire. They spent two weeks shuttling multiple sections of equipment between Milford Haven and a nearby beach.

‘Terra Marique’ was manoeuvred onto the beach by ‘Wilanne’ and ‘Wiltango’ in a precise operation.

The trucks were subsequently unloaded onto the barge, which was then towed away from shore by ‘Wilanne’ to be unloaded onto a larger cargo ship.

Timing and efficiency were vital on all sides to keep the project on schedule, as ‘Terra Marique’’s movements needed to be matched with the tides.

The entire project lasted approximately 3 weeks. ‘Willpower’ remained in Pembroke to tow ‘Terra Marique’ to its next job.