keyboard_arrow_left See all news

Recent News

06 Dec, 2022 /
Seawork Press FP
Investing to grow
A new pilot vessel’s higher transit speeds, even in challenging conditions, will enabl...
06 Dec, 2022 /
Seawork Press FP
Pushing the design envelope
Rising to meet the industry’s growing demand for lower carbon emissions, capacity and ...
05 Dec, 2022 /
Seawork Press FP
Keeping it close
Summer is well and truly over and the new custom pontoon at Brownsea Island, Dorset UK h...
01 Dec, 2022 /
Seawork Press FP
Future-proof hydrogen CSOVs on the way
A revolutionary new design of CSOVs with increased capabilities and flexibility has been...
01 Dec, 2022 /
Seawork Press FP
New delivery for challenging environments
An autonomous ‘air-ground payload transfer device’ with truly disruptive capabilitie...
Seawork Press FP
/ 14 Nov, 2022
keyboard_arrow_left See all news

Welcome workboat berth for Dover

The contract to supply and install a new workboat berth in Dover Harbour UK has been awarded to Inland and Coastal Marina Systems by the Dover Harbour Board.

Owing to the port’s exposed location and the size of the vessels destined to use the new facility, the project will consist of 7 x 19.65m reinforced concrete breakwater pontoons.

Weighing in at almost 100 tonnes each, the floating concrete units will have one metre of freeboard and, when combined, will be suitable for berthing working vessels up to 1000 tonnes displacement.

“We’re delighted to have been awarded this contract to design, manufacture and install the new workboat facilities at the Port of Dover,” says Maeve Parker, Senior Marina Engineer at ICMS.

“With the busy port’s location on the southeast coast being relatively exposed, we’ve created a bespoke design using our robust concrete breakwater units which are strong and durable enough to accommodate the port’s workboats and large commercial vessels, providing safe all year round berthing, and water access for crews, for a long time to come.”

The project, which is due to start installation in spring 2023, also includes the supply of floating foam fenders and M&E services.

Exhibitor; Inland and Coastal Marina Systems

 